PRINCE2 (PRojects IN Controlled Environments) is a widely recognized project management methodology used by organizations worldwide. The methodology provides a structured framework for effective project management, including the use of clear and concise project plans, defined roles and responsibilities, and regular progress reviews. PRINCE2 Foundation is the entry-level certification in the PRINCE2 certification pathway.
PRINCE2 Foundation exam covers various aspects of project management, including project organization, planning, control, risk management, quality management, and change management. It also covers the PRINCE2 principles, themes, and processes. PRINCE2-Foundation exam is a prerequisite for the PRINCE2 Practitioner certification, which is the next level in the PRINCE2 certification scheme.
NEW QUESTION # 207
Identify the missing word in the following sentence.
A project's [ ? ] are the measurable improvements resulting from the outcomes achieved through the use of the project's outputs.
- A. risks
- B. issues
- C. dis-benefits
- D. benefits
Answer: D
Explanation:
Section: Volume B
Explanation
A Benefit is the measurable improvement resulting from an outcome that is perceived as an advantage by one or more stakeholders.
Reference http://p2.tech-academy.co.uk
NEW QUESTION # 208
Which is a minimum requirement for applying the organization theme?
- A. To define the experience required for each project role
- B. To train project team members in the use of PRINCE2
- C. To include external stakeholders on the project board
- D. To document the project management team structure
Answer: D
Explanation:
Section: Volume B
Explanation
Explanation/Reference: http://prince2.wiki/Themes#Organization_Theme
NEW QUESTION # 209
Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?
- A. Learn from experience
- B. Continued business justification
- C. Manage by stages
- D. Manage by exception
Answer: C
Explanation:
Section: Volume B
Explanation/Reference: https://www.whatisprince2.net/prince2-theme-plans.php
NEW QUESTION # 210
Which product describes the roles and responsibilities for achieving the effective management of anticipated threats and opportunities in a project?
- A. Quality Management Strategy
- B. Communication Management Strategy
- C. Configuration Management Strategy
- D. Risk Management Strategy
Answer: D
NEW QUESTION # 211
Which may be funded from a risk budget?
- A. Impact analysis of requests for change
- B. Preparation of the Risk Management Strategy
- C. Implementation of a fallback plan
- D. Corrections due to off-specifications
Answer: C
NEW QUESTION # 212
According to the 'tailor to suit the project' principle, what is the basis for effective project management?
- A. That the appropriate information is provided to make decisions
- B. That the project method relates to the project's environment
- C. That the project is divided into an appropriate number of stages
- D. That the appropriate number and type of meetings are held
Answer: B
Explanation:
Explanation
Reference http://prince2.wiki/Tailor_to_suit_the_project_environment
NEW QUESTION # 213
How should the Team Manager report that tolerances are forecast to be exceeded?
- A. Create an Exception Report
- B. Create a Highlight Report
- C. Grant a concession
- D. Raise an issue
Answer: D
NEW QUESTION # 214
Which is a minimum requirement for applying the 'change' theme?
- A. Delegate the change authority to the senior supplier(s) for supplier off-specifications
- B. Specify in the change control approach the means by which project products will be protected
- C. Produce issue reports to document the impact assessment for requests for change
- D. Document the format and contents of the issue register
Answer: D
Explanation:
A minimum requirement for applying the 'change' theme in PRINCE2 is to document the format and contents of the issue register. This ensures that all issues, including requests for change, are captured systematically and managed appropriately throughout the project lifecycle.
= PRINCE2 7 Foundation handbook and online resources
NEW QUESTION # 215
Which PRINCE2 principle helps to address a concern that the project team may NOT have worked on a similar project?
- A. Focus on products
- B. Defined roles and responsibilities
- C. Learn from experience
- D. Manage by exception
Answer: C
Explanation:
The PRINCE2 principle of 'Learn from experience' addresses concerns about the project team's familiarity with similar projects. It mandates that project teams seek out and learn from previous relevant experiences and lessons logged in prior projects to enhance their effectiveness and efficiency, even when facing unfamiliar project scenarios. References: PRINCE2 Foundation Handbook, Learn from Experience principle section.
NEW QUESTION # 216
Which is part of quality control?
- A. Write Product Descriptions
- B. Document the customer's quality expectations
- C. Provide assurance that the project is being conducted properly
- D. Undertake quality reviews
Answer: D
Explanation:
Section: Volume B
Explanation
NEW QUESTION # 217
Which statement about the Directing a Project process is true?
- A. Covers the day-to-day activities of the Project Manager
- B. Provides a mechanism for the Project Board to assure that there is continued business justification
- C. Ensures there are regular progress meetings
- D. Begins on completion of the Initiating a Project process
Answer: B
Explanation:
The Directing a Project process in PRINCE2 provides the Project Board with a mechanism to ensure there is continued business justification for the project throughout its lifecycle. This process is crucial for maintaining the project's alignment with organizational objectives and for making decisions at key points such as stage boundaries. References: PRINCE2 Foundation official documentation and study materials.
NEW QUESTION # 218
Which is one of the six aspects of project performance that needs to be managed?
- A. Progress
- B. Security
- C. Risk
- D. Change
Answer: C
Explanation:
Section: Volume A
NEW QUESTION # 219
How often should the 'controlling a stage' process be used during a project?
- A. Once, for the whole project
- B. Twice, for initiation and for the rest of the project
- C. For each delivery stage in the project
- D. Whenever the project board meets
Answer: C
Explanation:
The 'Controlling a Stage' process should be used during each delivery stage of a project. This process is essential for the day-to-day management of the project stage by the project manager. It includes monitoring, reporting, and responding to issues within the stage to ensure the project remains within agreed tolerances.
= PRINCE2 7 Foundation handbook and online resources
NEW QUESTION # 220
Which describes a time-driven control?
- A. The expected frequency of progress reports specified in a work package
- B. The planned exception assessment meeting to authorize a requested exception plan
- C. The expected dates for planned checks of specialist products included in a stage plan
- D. The dates for the project's end stage assessment included in the project plan
Answer: A
NEW QUESTION # 221
Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,
- A. Management strategies
- B. Stakeholder interests
- C. Plan
- D. Time-driven controls
Answer: C
NEW QUESTION # 222
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?
- A. Provide the resources and skills to deliver the desired result
- B. Specify the benefits of the project
- C. Specify the desired result
- D. Pay for the project
Answer: A
NEW QUESTION # 223
The benefits Management approach has been reviewed by the project board to ensure there are sufficient benefit reviews after the project has closed.
Which principle is the project board applying?
- A. Focus on products
- B. Manage by stages
- C. Ensure continued business Justification
- D. Manage by exception
Answer: C
Explanation:
The principle of 'Ensure continued business justification' in PRINCE2requires that the project remains justified throughout its lifecycle. By reviewing the benefits management approach to ensure it includes sufficient benefit reviews after the project's closure, the project board is applying this principle to confirm that the project continues to provide value and that its benefits are realized as planned, even post-project.
References: = PRINCE27 Foundation Training Manual and official PRINCE2website documentation