[Q67-Q90] Try 100% Updated DCDC-003.1 Exam Questions [2026]

Share

Try 100% Updated DCDC-003.1 Exam Questions [2026]

Pass DCDC-003.1 Exam - Real Questions and Answers

NEW QUESTION # 67
What is the formula to find the maximum allowable cable depth in a non-solid bottom cable tray?

  • A. H = 50/1 + (L * 0.0007)
  • B. H = 100/1 + (L * 0.0007)
  • C. H = 150/1 + (L * 0.0007)
  • D. H = 200/1 + (L * 0.0007)

Answer: C


NEW QUESTION # 68
According to NEB, what is the recommended range for the low temperature in a data center?

  • A. 65 degrees
  • B. 60 degrees
  • C. 70 degrees
  • D. 75 degrees
  • E. 55 degrees

Answer: A


NEW QUESTION # 69
What is the Typical Voltage Of A Utility Sub-Station?

  • A. High voltage at a stunningly high rate
  • B. Medium to Low-voltage range between 270 to13800 volts
  • C. The United States uses only Direct Currents DC
  • D. Low voltage at 480 or less volts

Answer: B


NEW QUESTION # 70
What is the recommended height of a ceiling in a data center or telecommunications room?

  • A. 1112ft
  • B. 012 ft
  • C. 1015ft(correct)
  • D. 0

Answer: C


NEW QUESTION # 71
What is minimum recommended generator fuel storage amount?

  • A. enough to run 48-72 hours at full load
  • B. enough to run up-to a week at full load
  • C. enough to run 4 to 16 hours at full load
  • D. enough to run 24 to 36 hours at full load

Answer: A


NEW QUESTION # 72
What is the minimum required headroom for overhead cable tray?

  • A. 9"
  • B. 12"
  • C. 3"
  • D. 6"

Answer: D


NEW QUESTION # 73
Which network topology uses the least amount of cabling?

  • A. Top of Rack
  • B. Mesh
  • C. Bus
  • D. Star

Answer: A


NEW QUESTION # 74
Where is the recommended location for remote power panels?

  • A. inside a sealed room
  • B. outside the building
  • C. at one or both ends of an equipment row
  • D. suspended from ceiling

Answer: C


NEW QUESTION # 75
what additional fuel filtering is required for generators in class F3 and F4 facilities

  • A. four stage, paper-type fuel filters
  • B. two-stage, spin-on-type fuel filters
  • C. five stage, mesh type fuel filters
  • D. three stage, spin-on-type fuel filters

Answer: D


NEW QUESTION # 76
Where should all Storage and Unpacking activities occur?

  • A. Inside Computer Room
  • B. Outside Computer room, either in Storage Rooms or Staging Areas located adjacent to Computer Room with Dedicated air Handling
  • C. Outside the Building, at a secure location.
  • D. None of these
  • E. Near the Main Entrance of Data Center

Answer: B


NEW QUESTION # 77
What is the smoke development rating required for all materials hosted in a containment system?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: A


NEW QUESTION # 78
What are the different generator ratings?

  • A. Prime, Continuous and Standby
  • B. Primary, Secondary and Tertiary
  • C. Normal, Redundant and Fault-tolerant
  • D. Standard, Backup and Emergency

Answer: A


NEW QUESTION # 79
Where should power cable be ran in an access floor?

  • A. Cold aisle
  • B. Hot aisle
  • C. Below the access floor
  • D. Above the access floor

Answer: A


NEW QUESTION # 80
When is a battery room required to have electrolyte spill containment and exhaust systems?

  • A. When the ceiling suspended load capacity is below 20 pounds per square foot
  • B. When corrosive fumes are detected in operation room
  • C. when the potential for outgassing hydrogen exists
  • D. when the battery weight exceeds 500 pounds

Answer: C


NEW QUESTION # 81
What is the recommended level of redundancy for a critical power system in a Tier III data center?

  • A. 2N
  • B. 3N
  • C. N+1
  • D. 2N+1
  • E. N

Answer: C


NEW QUESTION # 82
What is the recommended raised floor height, especially for high density needs and underfloor HVAC?

  • A. 30"
  • B. 42"
  • C. 24"
  • D. 36"

Answer: D


NEW QUESTION # 83
What kind of height clearance should data center access roads have?

  • A. None Of The Above.
  • B. A Minimum clear road width with fourteen (14)ft hight clearance throughout.
  • C. A Minimum clear road width and sixteen (16) ft height clearance throughout.
  • D. A Minimum clear road width and six(06) ft height clearance throughout.

Answer: B


NEW QUESTION # 84
where is the storage room located?

  • A. All
  • B. outermost point of Data Centre
  • C. next door to computing area
  • D. away from computer room, adjacent to equipment entrance at data center
  • E. Near Backup Generator

Answer: D


NEW QUESTION # 85
What is the recommended amount of fuel supply needing to be available to a class F3 data center?

  • A. 96 hours
  • B. 48 hours
  • C. 24 hours
  • D. 72 hours

Answer: D


NEW QUESTION # 86
What is the NEBS GR-3028-CORE recommended operational temperature.

  • A. Up To140 Degrees Fahrenheit /60 Degrees Celsius
  • B. -20°F/-28° C minimum and up to a maximum of104 ° Fahrenheit/40° Celsius
  • C. -30°F to +110°F (-34°C to +43°C)
  • D. -25°F to +125°F (-32°C to +52°C)

Answer: B


NEW QUESTION # 87
What are the factors that affect availability?

  • A. Operational Requirements
  • B. All of the above
  • C. Impact of Downtime
  • D. Operational Availability

Answer: B


NEW QUESTION # 88
What is the difference between a hard-wired and a plug-in UPS?

  • A. Plug-in UPS is more cost-effective than hard-wired UPS
  • B. Hard-wired UPS is more efficient in terms of power delivery than plug-in UPS
  • C. Hard-wired UPS is permanently connected to the electrical system while plug-in UPS can be easily connected and disconnected
  • D. Hard-wired UPS is more reliable than plug-in UPS

Answer: C


NEW QUESTION # 89
what is the maximum recommended elevation for a data center

  • A. 1,000 ft
  • B. 10,000 ft
  • C. 5,000 ft
  • D. 15,000 ft

Answer: B


NEW QUESTION # 90
......

DCDC-003.1 Exam Questions Get Updated [2026] with Correct Answers: https://www.test4engine.com/DCDC-003.1_exam-latest-braindumps.html

Free BICSI DCDC-003.1 Test Practice Test Questions Exam Dumps: https://drive.google.com/open?id=18pIvMxKMAckKTs0gRcpaYXH86YjmbvSx