NEW QUESTION 54
Which is a purpose of a Lessons Report?

  • A. Provide a summary of the benefits realized during the project
  • B. Detail open issues and risks that need to be managed after the project has closed
  • C. Compare the actual performance of the final stage against its plan
  • D. Improve the project management method for future projects

Answer: D

 

NEW QUESTION 55
Identify the missing words in the following sentence.
A benefit of adopting PRINCE2 is that it can be applied to [ ? ] - and can easily be implemented alongside specialist techniques.

  • A. any type of project
  • B. business as usual
  • C. programmes and projects
  • D. all types of programmes

Answer: A

 

NEW QUESTION 56
Which is a purpose of the Risk Register?

  • A. Act as a repository for informal issues
  • B. Describe the risk management techniques and standards to be applied to the project
  • C. List the responsibilities for achieving an effective risk management procedure
  • D. Act as a central record of information relating to the identified risks for the project

Answer: D

 

NEW QUESTION 57
To meet the minimum requirements for applying the progress theme, what must be considered?

  • A. How time-driven reports will be produced
  • B. Which management products will be baselined
  • C. Who is responsible for reporting on progress
  • D. How lessons will be learned

Answer: A

Explanation:
Section: Volume B
Explanation
Explanation/Reference: http://prince2.wiki/Themes

 

NEW QUESTION 58
Which is a purpose of the quality theme?

  • A. To establish baselines against which any changes to products can be assessed
  • B. To establish how the project will ensure that all products created meet their requirements
  • C. To identify all the products of the project to ensure the scope has been adequately defined
  • D. To determine the communication needs of the organization's quality assurance function

Answer: B

Explanation:
Section: Volume B

 

NEW QUESTION 59
Which is part of quality control?

  • A. Provide assurance that the project is being conducted properly
  • B. Document the customer's quality expectations
  • C. Write Product Descriptions
  • D. Undertake quality reviews

Answer: D

Explanation:
Section: Volume B
Explanation/Reference:

 

NEW QUESTION 60
Which is a purpose of a quality register?

  • A. To record the date a completed work package was received
  • B. To provide the status of quality activities carried out for completed products
  • C. To record cross-references to issues relating to the quality of the products
  • D. To capture quality concerns about completed products

Answer: A

Explanation:
Section: Volume B

 

NEW QUESTION 61
Which is a recommended quality review team role?

  • A. Administrator
  • B. Assurance
  • C. Project Support
  • D. Project Manager

Answer: A

Explanation:
Section: Volume B
Explanation/Reference:

 

NEW QUESTION 62
Which describes an off-specification?

  • A. An interdependency between products that was previously unidentified
  • B. A prototype demonstrating a possible design solution
  • C. The addition of an improvement to a product description
  • D. The production of more than the defined quantity of a specialist product

Answer: A

Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-change-control/

 

NEW QUESTION 63
Which is a purpose of an End Project Report?

  • A. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
  • B. Identify individuals or groups that need to be told that the project is coming to an end
  • C. Review how well the project performed against the Project Initiation Documentation used to authorize it
  • D. Ensure that key project information is archived and made secure

Answer: C

Explanation:
Section: Volume B

 

NEW QUESTION 64
Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?

  • A. Defined roles and responsibilities
  • B. Manage by exception
  • C. Manage by stages
  • D. Continued business justification

Answer: B

Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Manage_by_exception

 

NEW QUESTION 65
Why is a Project Brief produced?

  • A. To record the strategies and management controls to be used by a project
  • B. To be used by the Project Board as a basis for reviewing the progress of a project
  • C. To provide a full and firm foundation for the initiation of a project
  • D. To act as a trigger for the Starting up a Project process

Answer: C

Explanation:
Section: Volume B

 

NEW QUESTION 66
Which is a purpose of the change theme?

  • A. To identify, assess and control any potential and approved changes to baselined products
  • B. To assess and control uncertainty
  • C. To prevent change to baselined products
  • D. To establish mechanisms to monitor and compare actual achievements against those planned

Answer: A

Explanation:
Section: Volume B
Explanation/Reference: https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-prince2-change- theme

 

NEW QUESTION 67
Which is a typical core activity within configuration management?

  • A. Issue management
  • B. Quality inspection
  • C. Identification
  • D. Preparation

Answer: C

 

NEW QUESTION 68
Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

  • A. Risk
  • B. Unique
  • C. Cross-functional
  • D. Change

Answer: C

Explanation:
Section: Volume A

 

NEW QUESTION 69
......