NEW QUESTION 54
As part of maintaining (importing new employees that were added last week) project enterprise labor resources in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update resources based on changes In HCM. You define maintenance conditions on the Manage Project Enterprise Labor Resource page to process both employees and contingent workers.
Which three are parameters that are based on which the system identifies the new resources?
- A. Department
- B. Jobs
- C. Project Unit
- D. Organization
- E. Business Unit
Answer: B,D,E
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/fapfm/implementing-project-execution-management-applications.html#FAPFM1718570 Topic - Manage Maintenance Conditions for Project Enterprise Labor Resource
NEW QUESTION 55
When implementing Project Performance Reporting, your customer has the following requirements:
Every time a project cost is greater than or equal to a threshold, then the project should be shown as critical.
As long as a project cost is less than the threshold, the project should be shown as on-track.
Which threshold level rule is ideal for this kind of KPI definition? (Choose the best answer.)
- A. multiple threshold levels
- B. single threshold level range
- C. single threshold level value
- D. multiple threshold level value
Answer: C
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/oapjs/update-project-performance-data-and-generate-kpis.html#OAPJS16654 Performance Status Indicator Performance status indicators give an immediate picture of the status of a project, such as critical, at risk, and on track. Each distinct icon indicates the status and severity of performance. During KPI definition, you first associate status indicators with performance statuses:
Critical
Severe
At risk
On track
Ahead
You then associate these statuses with threshold levels. When KPI values are generated for a project, each value is compared to the defined thresholds and the corresponding status indicator for the KPI appears on project performance reports.
A status can identify negative performance so that you can take the appropriate actions to prevent or quickly resolve problems. Conversely, a status can identify positive performance to help you track expected or excellent performance.
https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19b/fapfm/implementing-project-financial-management-applications.html#FAPFM975706 Create Key Performance Indicators Create key performance indicators (KPI) to measure how well your organization performs an operational, tactical, or strategic activity that is critical for the current and future success of the organization.
Note: To create KPIs you must enable a project unit to track key performance indicators.
Use the Threshold Levels section to specify thresholds to indicate the health status of a KPI. Select one of the following options:
Multiple threshold levels
Single threshold level value
Single threshold level range
NEW QUESTION 56
Your customer wants to assign the Net 45 payment term to all sets except for the corporate business unit specific set, which is assigned the Net 15 payment term. At transaction entry, the list of values for payment terms consists of only one set of data: the set that is assigned to the transaction's business unit.
Which reference data sharing method would you set up to meet the customer requirement? (Choose the best answer.)
- A. assignment to one set only with common values
- B. assignment to one set only; no common values allowed
- C. assignment to multiple sets; common values allowed
- D. assignment to multiple sets; no common values allowed
Answer: D
Explanation:
Reference https://docs.oracle.com/en/cloud/saas/applications-common/19b/facia/define-enterprise-structures.html#FACIA462453 Reference Data Sharing Methods Variations exist in the methods used to share data in reference data sets across different types of objects. The following list identifies the methods:
Assignment to one set only, no common values allowed. This method is the simplest form of sharing reference data that allows assigning a reference data object instance to one and only one set. For example, Asset Prorate Conventions are defined and assigned to only one reference data set. This set can be shared across multiple asset books, but all the values are contained only in this one set.
Assignment to one set only, with common values. This method is the most commonly used method of sharing reference data that allows defining reference data object instance across all sets. For example, Receivables Transaction Types are assigned to a common set that is available to all the business units. You need not explicitly assign the transaction types to each business unit. In addition, you can assign a business unit-specific set of transaction types. At transaction entry, the list of values for transaction types includes the following:
Transaction types from the set assigned to the business unit.
Transaction types assigned to the common set that is shared across all business units.
Assignment to multiple sets, no common values allowed. The method of sharing reference data that allows a reference data object instance to be assigned to multiple sets. For instance, Payables Payment Terms use this method. It means that each payment term can be assigned to one or more than one set. For example, you assign the payment term Net 30 to several sets but assign Net 15 to a set specific only to your business unit. At transaction entry, the list of values for payment terms consists of only the set that is assigned to the transaction's business unit.
Note: Oracle Fusion Applications contains a reference data set called Enterprise. Define any reference data that affects your entire enterprise in this set. Also update the data set going forward as you create new reference data items.
NEW QUESTION 57
Your organization performs revenue recognition based on the Labor and Non-labor Burden schedule types. Identify the setup required to enable this kind of revenue recognition. (Choose the best answer.)
- A. Create a revenue method with a revenue method classification of Amount Based.
- B. Create a revenue method with a revenue method classification of Rate Based.
- C. Create a revenue method classification with a revenue method of Percent Spent.
- D. Create a revenue method classification with a revenue method of Percent Complete.
Answer: B
NEW QUESTION 58
Your customer has a requirement to import and process third-party transactions that are "costed" and "accounted".
Which configuration option needs to be set satisfy the requirement? (Choose the best answer.)
- A. Transaction Source Options
- B. Import Options
- C. Document Entry Options
- D. Document Options
Answer: A
Explanation:
Reference https://docs.oracle.com/cd/E51367_01/projectop_gs/OAPJC/F1071488AN1004C.htm
NEW QUESTION 59
Which step within the functional setup manager helps you to move your verified setup data from the test environment to a production environment?
- A. Setting Up
- B. Deploying
- C. Planning
- D. Opting In
- E. Maintaining
Answer: A
NEW QUESTION 60
Identify three correct statements about project types. (Choose three.)
- A. Classifications can be assigned at project type.
- B. Project type can be associated with multiple project units.
- C. Summarization options can be specified at project type.
- D. Project type can be used as a source in subledger accounting.
- E. Project type can be enabled for both billing and capitalization.
Answer: A,D,E
NEW QUESTION 61
Which three are valid password complexity criteria while setting up password policies? (Choose three.)
- A. Simple: At least 8 characters and 1 number
- B. Complex: At least 8 characters, 1 uppercase, and 1 number
- C. Very Complex: At least 6 characters, 1 uppercase, 1 number, and 1 special character
- D. Very Complex: At least 8 characters, 1 uppercase, 1 number, and 1 special character
- E. Very Complex: At least 8 characters, 1 uppercase, 1 number, and 2 special characters
Answer: B,D,E
NEW QUESTION 62
Identify the precedence order in which cost rates are determined for a planning resource when deriving raw costs for rate-based planning resources. (Choose the best answer.)
- A. Job rate schedule > Resource class rate schedule > Override rate > Person rate schedule
- B. Person rate schedule > Job rate schedule > Resource class rate schedule > Override rate
- C. Override rate > Job rate schedule > Resource class rate schedule > Person rate schedule
- D. Resource class rate schedule > Override rate > Job rate schedule > Person rate schedule
- E. Override rate > Person rate schedule > Job rate schedule > Resource class rate schedule
Answer: E
Explanation:
Reference https://fusionhelp.oracle.com/helpPortal/topic/TopicId_P_8718794B26A7BB93E040D30A688149A3
NEW QUESTION 63
You create a contract with two contract lines: Line 1 and Line 2. You create separate bill plans: A for contract Line 1 and B contract for Line 2, with a different bill set number (11 for Bill Plan A and 22 for Bill Plan B).
Then Bill Plan A is allocated against Project X - Task 10, and Bill Plan B is allocated against Project Y - Task 30.
Based on the preceding setup, you are generating invoices. Identify two correct statements about invoice generation in this scenario. (Choose two.)
- A. Both the contract lines create only a single invoice because they are using the same contract.
- B. Two invoices are created using the same contract.
- C. Bill set number drives the grouping of transactions.
- D. Invoice generation does not depend on bill plan. The invoices are created based on the contract line.
Answer: B,C
Explanation:
Ref: https://docs.oracle.com/cd/E51367_01/projectop_gs/OAPJB/F1087456AN1006D.htm What's a bill set?
Transactions originating from different bill plans with the same bill set number on a contract are included on the same invoice. If a contract has multiple bill plans and each have different values for the bill set, Oracle Fusion Project Billing creates a separate invoice for each bill plan
NEW QUESTION 64
Stigma consulting has been hired by a client to implement Project Management Cloud. Which role should they assign to a user for using the rapid implementation feature to set up the Project Financial Management offering by populating and uploading a Microsoft Excel workbook?
- A. Project Administrator
- B. Project Executive
- C. Project Application Administrator
- D. Project Integration Specialist
Answer: A
NEW QUESTION 65
Which two statements are true about the borrowed and lent cross charge method? (Choose two.)
- A. This method creates accounting entries that move an amount equal to the transfer price between the provider and receiver organizations
- B. Internal Invoice is not generated with this method.
- C. You must set up a contract business unit to use this method.
- D. This method allows you to process cross charge transactions across legal entities.
Answer: B,C
NEW QUESTION 66
Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets based on the construction-in-process cost of each asset. Identify the asset allocation method that you must use as the default method while configuring project types to meet this requirement. (Choose the best answer.)
- A. Estimated Cost
- B. Actual Unit
- C. Standard Unit Cost
- D. Current Cost
- E. Spread Evenly
Answer: D
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapfm/project-foundation-configuration-manage-project-types.html#OAPFM220111 Topic - Asset Cost Allocation Methods: Explained The asset cost allocation method determines how indirect or common costs incurred on a project are allocated to multiple assets.
You can specify an asset cost allocation method to enable Oracle Fusion Project Costing to automatically allocate unassigned asset lines and common costs across multiple assets. Unassigned asset lines typically occur when more than one asset is assigned to an asset grouping level.
Projects and project templates inherit a default asset cost allocation method from the associated project type. You can override the default at the project level. If you use capital events to allocate costs, then you can also override the asset cost allocation method at the event level.
The following table describes the available asset cost allocation methods.
Method
Basis of Cost Allocation
Actual Units
Number of units defined for each asset
Current Cost
Construction-in-process (CIP) cost of each asset
Estimated Cost
Estimated cost of each asset
Standard Unit Cost
Combination of the standard unit cost and the number of units defined for each asset Spread Evenly Equal allocation of cost to each asset
NEW QUESTION 67
After completing setups in a source environment, your customer wants to move the setup data to a target environment. Identify the two statements related to task list scope, which you must consider before taking a decision based on the customer requirement. (Choose two.)
- A. Exported setup data can be filtered by specific scope values if the business object has scope enabled for the setup data export.
- B. Exported setup data cannot be filtered by specific scope values if the business object has scope enabled for the setup data export.
- C. A scope value is used to assign users who can perform a task within an implementation project.
- D. A task list can be segmented by a scope value and a task can be performed for each qualifying value of the selected object.
Answer: A,D
Explanation:
Reference https://docs.oracle.com/cd/E60665_01/common/OAFSM/OAFSM1166430.htm#OAFSM1166426
NEW QUESTION 68
You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem. (Choose two.)
- A. Pending burden summarization items have not been processed.
- B. The corresponding Oracle Payables Cloud accounting period has not been closed.
- C. Unaccounted transactions have not been swept to the next period.
- D. Transactions entered in an integrated Oracle Cloud Application are accounted, but not yet transferred and imported into Oracle Project Portfolio Management Cloud.
- E. Unaccounted transactions are not imported.
Answer: C,D
Explanation:
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapjb/record-accounting-for-project-billing.html#OAPJB340382 Topic - Accounting Period and Project Accounting Period Closing: How Validation Works
NEW QUESTION 69
Identify the three contract attributes from Project Performance Data that are used in Project Performance dashboard regions. (Choose three.)
- A. Projects
- B. Contract Header
- C. Task
- D. Expenditure Type
- E. Contract Line
Answer: A,C,E
Explanation:
Reference https://docs.oracle.com/cloud/farel9/projectcs_gs/FAUAR/F1537947AN10251.htm
NEW QUESTION 70
Your organization has a requirement to create and apply a new theme for the application user interface.
Which option allows you to achieve this requirement?
- A. Structure Page
- B. Setup and Maintenance Work Area
- C. Appearance Page
- D. User Interface Text
Answer: C
NEW QUESTION 71
You have defined two expenditure types, but they are not available for selection when you enter an expenditure batch. Identify the reason for this problem. (Choose the best answer.)
- A. The two expenditure types are not assigned to the reference data set that is assigned to the business unit in which the transaction is performed.
- B. The two expenditure types are not assigned to the reference data set that is assigned to the project-owning organization in which the transaction is performed.
- C. The two expenditure types are not assigned to the reference data set that is assigned to the project expenditure organization in which the transaction is performed.
- D. The two expenditure types are not assigned to the reference data set that is assigned to the project unit in which the transaction is performed.
Answer: D
Explanation:
Ref: Implementing-Project-Financial-Management-and-Grants-Management.pdf (19A Part # F11256-01) Chapter 3 - Define Project Organizations Topic - Set Assignments and Project Data - How They Work Together (Page 29) Business Unit as Set Determinant Business units enable you to control and report on financial transactions, usually for specific geographical entities within the enterprise. For project management purposes, assign the Project Accounting business function to the business unit.
Business unit is a set determinant for the project-related reference data objects described in the following table.
Ref Data Object
Entities
Project Accounting Definition
Project Types
Project Rates
Project rate schedules
Project Unit as Set Determinant
Use project units to enforce consistent project management practices across your enterprise. Project unit is a set determinant for the reference data objects described in the following table.
Ref Data Object
Entities
Project Definition
Class codes, financial plan types, project plan types and project roles Project Transaction Types Expenditure types and work types You can only select class codes, plan types, roles, expenditure types and work types that are assigned to the same set as the project unit. To enable expenditure types and work types for use on projects owned by a project unit, assign the set associated with the Project Transaction Types reference data object to those entities
NEW QUESTION 72
Which component provides a human workflow service that handles all interactions with users or groups in business processes?
- A. Security Console
- B. Subledger Accounting
- C. SOA Suite
- D. BPM Worklist
Answer: C