NEW QUESTION 51
To modify the micro-module view of ECC800,users need to log in the WebUI as as admin.
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION 52
2.4G antenna of ECC800 should be connected to ( ).
- A. RS485 port
- B. 3G/4G antenna interface
- C. RF_ZA line interface
- D. DO output dry contact
Answer: B
NEW QUESTION 53
The default user name of ECC800 is admin, and admin has permission to operate on the ECC800 WebUI.
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION 54
On the NetEco interface, a modular can only bind () ECC800 devices.
- A. 0
- B. 1
- C. 2
- D. 3
Answer: B
NEW QUESTION 55
When four UPS2000-G-20K parallel setting is "3+1", the capacity of the system is ( ) KVA.
- A. 0
- B. 1
- C. 2
- D. 3
Answer: D
NEW QUESTION 56
The Maximum distance of WIFI coverage for WIFI converter is ( )m.
- A. 0
- B. 1
- C. 2
- D. 3
Answer: C
NEW QUESTION 57
The DX air cooled air conditioner has no limit on the installation distance.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION 58
The NetEco system can customize the alarm sound for different levels of alarms.
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION 59
On the ( ) menu of NetEco App. PUE information can be displayed.
- A. Power
- B. Aisle
- C. Alarm
- D. Log management
Answer: A,B,C,D
NEW QUESTION 60
DuringNetCol5000-C commissioning, the opening of the water valve needs to be adjusted to minimum when you inject water and exhaust air.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION 61
The EPO ports of UPS5000-E can be selected to normal open or normal close.
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION 62
When the UPS5000-E (), boot will automatically run the Quick Setup Wizard. (Multiple Choice)
- A. First boot
- B. Start after recovery failure
- C. Turn it off and then on.
- D. The device is turned on again after the factory settings are restored.
Answer: A,D
NEW QUESTION 63
Commissioning UPS5000-E parallel system, the reason for triggering EPO ports is ().
- A. To protect batteries and prevent battery discharge
- B. To protect loads against electric shock and ensure safety
- C. To power off the loads and prevent damage to the loads.
- D. To disconnect the output and set the parallel parameters
Answer: C
NEW QUESTION 64
Which of the following options is a natural cooling system?
- A. Water-cooled cold air conditioning system
- B. Air-cooled direct expansion air conditioning system
- C. Water-cooled cold water air conditioning system
- D. Direct ventilation air conditioning system
Answer: D
NEW QUESTION 65
The work modes of rotary wheel free cooling solution are ().
- A. Direct ventilation mode
- B. Mixed mode
- C. Compressor cooling mode
- D. Free cooling mode
Answer: B,C,D
NEW QUESTION 66
When you create a camera in NetEco, you need to get () in addition to the IP address of the camera.
- A. Camera pixels
- B. Camera brightness
- C. Camera installation location
- D. Camera coding
Answer: D
NEW QUESTION 67
In the battery model 6-GFM-150, 150 indicates the battery ().
- A. Maximum capacity
- B. Rated capacity
- C. Minimum capacity
- D. Actual capacity
Answer: B
NEW QUESTION 68
UPS2000-A-(1-3kVA) closes the mains input switch and directly enters the bypass working state.
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION 69
Where is the recommended installation location for the Smart ETH socket?
- A. Side of the cable trough on the top of the cabinet
- B. Inside the network cabinet
- C. Control skylight
- D. Inside the threshold
Answer: A
NEW QUESTION 70
Domains can be created in NetEco, such as campuses, buildings, machine rooms, containers, etc.
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION 71
For the half sized NetCol5000-A25 kW, when preserve positive pressure, the pressure is ( ) MPa
- A. 0
- B. 1
- C. 2.5
- D. 0.8
Answer: B
NEW QUESTION 72
When turning on the maintenance bypass switch of UPS5000-E, to make sure loads continue to be powered, which should be noted?
- A. If the UPS works in normal mode you can turn on the maintenance bypass switch
- B. Shutdown the inverter, switch the UPS to bypass mode and turn on the maintenance bypass switch
- C. If the UPS works in ECO mode, you can turn on the maintenance bypass switch
- D. Perform EPO and turn on the maintenance bypass switch
Answer: B